The Versailles City Council was informed at last week’s regular meeting

by Mayor Brian Traugott that it could lose $14,000 as a result of the

failure of H&N Lights (H&N) to complete a contracted lighting project.

H&N is the business the city contracted with for the installation of

roofline lighting on Main Street as part of the revitalization plan.

Several businesses, including The Woodford Sun, had agreed to permit the

installation of the lights along the street-facing top of their facades.

The roofline lighting project was budgeted by the council for this

fiscal year. H&N quoted a cost of about half of the budgeted amount and

so the city entered into an agreement with it. The $24,000 total cost

was split between the city and the Woodford County Tourism Commission,

with the city contributing $14,000 and the commission $10,000. H&N had

previously installed the roofline lights at the courthouse and Amsden

building.

Traugott advised that no action needed to be taken (at the meeting) but

said, “At the risk of slander, I think we have been scammed, perhaps.”

Bill Moore, the city attorney, said that “truth is a defense to slander.”

In a follow-up interview, Traugott said, “It wasn’t so much a scam as

perhaps Holzman having problems, it’s just too early to tell.”

The possible financial loss came to light when Traugott said he had

grown “frustrated” with the lack of communication and performance by

H&N. On the recommendation of Moore, Traugott demanded the company

return the money. Hannah Holzman, the contact for H&N, told him that she

would “love to (give a refund) but the lights had been purchased, sized,

cut and solar boxes ordered.” Traugott requested Emily Downey, executive

director of the Tourism Commission, to follow up with Holzman to request

H&N turn over the materials that had arrived and to tell her that the

city would do the installation. Traugott said since leaving the message,

“Emily has been ghosted.”

Councilmember Laura Dake said she understood that Holtzman had left

Kentucky, and Traugott said, “That is the rumor.”

Versailles Police Chief Mike Murray advised the council that his

department would open an investigation and do all they could if

requested. Several council members expressed their support for an

investigation. Murray said the crime of theft of services could possibly

be used.

Traugott said, “This is a little embarrassing . . . we will get (the

lighting project) done eventually.”

Traugott confirmed that the city had formally turned the matter over to

the Versailles Police Department and that a detective was already

investigating.

In a separate interview, Traugott said the original deal was entered

into in good faith, but at this point the city would make every effort

to retrieve the taxpayer’s money.

“We’re not taking lightly that there’s taxpayer money that’s been

expended – either ours or tourism’s, which is an entity of ours,” he

said. “We’re not taking that lightly. We’re going to pursue every effort

to recover what we can.”

Deputy Chief Rob Young did not return a call for comment. Lee Howard,

the chairman of the Tourism Commission, did not respond to messages for

comment.

Technical difficulties

Versailles City Council live streams its council meetings on its

Facebook page. However, according to that site, technical difficulties

prevented the meeting from being shown live. However, the meeting was

video-recorded and is now on its Facebook page, “City of Versailles,

Ky”. The link to video recordings of council meetings can be found at

https://versailles.klc.org/Blog/43/city-council-meeting-videos-and-minutes.

However, it does not appear to have any recorded meetings since August

15, 2023, so a Facebook account is necessary to view the Nov. 21 meeting.

Downtown Revitalization

Ken Kerkhoff, the chair of the Versailles Downtown Revitalization

committee provided an update on the progress of the project. Kerkhoff

said he was very excited about the schedule as construction has

progressed ahead of schedule with the good weather and they were looking

at newer monetization and marketing possibilities. He said that nearly

all of the underground work had been completed with a few setbacks –

digging led to the discovery of an old dump and its removal necessitated

backfill.

Kerkhoff said that construction on the pavilion structure will soon

start and that “people will really get excited when they start seeing

the above-ground happening.” He also said that any additional costs that

have been incurred due to the need for backfill will be offset with

other savings. He also showed the council a slide of a mock-up of the

main entry which will be at Main and Court Streets and have large

columns supporting an arch-type structure spanning Court. Kerkhoff

described this as “Versailles’ front door”. He hopes to have a more

detailed rendering to show council in December.

Parts of the project will necessitate obtaining easements from the

Fiscal Court, Kerkhoff said, and he plans to go before the court soon to

work that out.

Special Projects

Coordinator

Traugott presented the council with a revised position description for

the newly created Special Projects Coordinator or Main Street Manager –

Councilmember Lisa Johnson pointed out that the position may need to be

re-named the latter title if the city chooses to seek grant funds from

the Kentucky Main Street Program. The position will be responsible for a

cornucopia of duties related to the ongoing revitalization project,

downtown events such as parades and markets, serving on the tourism

commission, event planning at the farmers market and stage, and “other

duties that may be assigned by the mayor.” The position will require a

high school diploma or equivalent plus five years’ experience in either

or both event planning or communications/marketing.

The position will be at the level of other department heads on the

organizational chart. Traugott said he would post the position shortly

after Thanksgiving.

Shire Village road

The homeowner’s association (HOA) of Shire Village, a development off

Beasley Road, following a vigorous debate and close vote according to

Traugott, has requested the city accept Rumsley Circle as a city road.

Rumsley Circle is the only road in the development. Traugott advised

that in anticipation of the city’s requirements for acceptance, the HOA

had the street paved last year, which should mean no repaving will be

needed for 20 years according to Bart Miller, the Public Works director.

The city is already providing emergency services to the neighborhood. By

accepting, the city would plow the road and be responsible for general

maintenance, but it would be owned by taxpayers and no longer private.

The HOA would also have to agree to no on-street parking due to the

width of the road.

Traugott said that before the road, which is now private, could even be

considered for full acceptance the Planning Commission would need to

approve an amended plat and various deed issues resolved. Given the

legal costs of the new plat and deed fixes, Traugott said it was

appropriate, if the council agreed, to give conditional approval now and

then once the amended plat is approved by the commission and the deed

issues are resolved to then formally accept the street. The council

unanimously approved the conditional acceptance.

Board appointments

Council approved the reappointment of Tony Hardin to the Joint Board of

Ethics, Cathy Weil to the Code Enforcement Board and Rev. Tony Wilson to

the Versailles Housing Authority.

Leave a comment

Your email address will not be published. Required fields are marked *